The Oregon Department of Transportation reports that the I-5 southbound off-ramp at the Mt. Ashland Exit 6 will close for 12 hours beginning Tuesday, August 2 at 6:00 a.m. for paving. Traffic bound for the exit will need to use alternate routes such use Oregon 273. The ramp will remain open for emergency service traffic.
The Exit 6 southbound on-ramp will close August 4-17 for corrective work on the Exit 6 bridge deck over Old Siskiyou Highway. Southbound I-5 traffic should use Oregon 273 to Exit 1 to access I-5. Mainline southbound I-5 traffic over the bridge will narrowed to a single lane to complete the work.
The paving and corrective work are some of the last items needed to complete the multi-year $32 million project that improves 11 miles of I-5 from the California border to Ashland.
I-5 Work Remaining…
Work still to come before the project is complete this fall includes shoulder paving, new guardrail, wiring six new electronic message signs, final striping and installing recessed pavement markers.
On the road? Why not take us with you. All our websites are mobile-friendly. Visit our growing family of exit guides: I-4 Exit Guide, I-5 Exit Guide, I-10 Exit Guide, I-75 Exit Guide, and I-95 Exit Guide. Detailed exit service listings… discount lodging, camping, food, gas and more for every exit along the way!